2. Road Construction Practice
2.1 The Road Construction Process
The type of road construction used varies from one
job to another. The type of construction adopted for a particular road depends
on:
- the volume and nature of traffic to use the
road,
- the nature of the materials available,
- the topography,
- foundation conditions,
- type and availability of construction equipment,
and
- financing arrangements and timing.
Any road construction job consists of number of
basic steps, although the relevant importance and the interaction between
these steps will vary from job to job. These steps can be summarised as:
- planning, programming and pre-construction
activities;
- site clearance;
- setting out;
- earthworks;
- bridge construction;
- drainage structures;
- pavement construction;
- placement of road surfacing;
- placement of road furniture; and
- landscaping.
LINKS TO SITES ON ROAD CONSTRUCTION.
Main Roads Queensland has a
List of Projects
at their Web site which gives details of major road works being undertaken
around Queensland.
The
NSW Roads and Traffic Authority
site includes a section which gives some details of major road building
projects around NSW.
2.2 Pre-Construction Activities
2.2.1 Propery Acquisition
Property acquisition may take considerable time,
and may be a very emotive issue for land owners involved.
2.2.2 Public Utility and Property Adjustments
In rural areas public utility adjustments rarely
constitue major work and the main property adjustment work is fencing new
boundaries and restoring property accesses. In urban areas public utility
adjustments may be complex and extensive. Consequently they may be very costly,
take a long time, and require a lot of coordination.
2.2.3 Cost Estimates
Detailed cost estimates are required for all construction
jobs prior to commencement.
2.2.4 Pre-construction Investigations
These include geotechnical surveys and consideration
of available labour, plant and materials.
2.2.5 Work Planning
Construction activities are summarised onto some
form of job control diagram such as a bar chart or Critical Path Network.
This work must be done before the job commences and also periodically updated
as the job progresses.
2.2.6 Commencement
The first activities on site are usually the establishment
of site offices, the construction of compounds to ensure security for plant
and materials, and the provision of facilities (eg meal rooms, change rooms)
for the workforce.
2.3 Site Clearance
The method used depends upon the extent of the task,
the type of country, the time available, and the equipment and labour available.
Clearing usually involves the removal of vegetation such as grass, brush,
trees and stumps, but may also include the removal of old buildings, structures,
etc.
The most commonly used item for clearing is the bulldozer,
although scrapers and graders may also be used. A dozer may affect clearing
by pushing but pulling with a rope, or the use of explosives, may be required
with large trees. Clearing by chainsaw can only be used if the stumps can
be left behind (which is not usually the case - stumps will rot away leading
to subsidence of overlying material).
Consideration must be given as to how cleared material
is to be disposed of. Timber may be burnt if environmental conditions allow,
but otherwise it has to be carted away and disposed of as landfill.
Following clearing operations, topsoil should be
stripped and stockpiled for future landscaping. Topsoil is unsuitable for
embankment or road building, and it is a valuable resource which should
be handled and used thoughtfully.
2.4 Setting Out
The object of setting out is to mark on the site
actual positions and ruling dimensions for the guidance of plant operators
and supervisors.
Setting out may involve two phases:
- establishment of a centreline (and suitable
recovery markers for use if the centre markers are destroyed) and marking
of the limits of the area to be cleared; and
- after clearing, the more detailed location of
the formation together with level control.
Setting out will therefore involve the placement
of a pegged centreline, placement of recovery pegs, placement of clearing
stakes, establishment of batter pegs (and batter profiles for larger cuts
and fills), and pavement control markers.
2.5 Earthworks
The eventual aim of the earthworks phase of the
construction is to position the subgrade underlying the pavement layers
in the right location and at the correct level, and to provide drainage.
The operations to be performed are:
- formation of cuttings by excavating through
high ground,
- formation of embankments by filling over
low ground,
- shaping the finished surface to design levels,
and
- excavating for drainage works.
The earthworks is often the largest task in the
road building process and therefore careful planning and organisation are
essential. Speed and efficiency depend very much upon the quantity and types
of earthmoving plant available.
2.5.1 Sequence of Operations
The normal sequence of operations in cut and fill
work is:
- In Cut
- excavate to the depth necessary to reach
formation level,
- transport away from the site undesirable
material such as organic soils,
- haul suitable materials from cuts to fill
areas, and
- suitably dispose of any excess cut material.
- In Fill
- drain water from depressions and dispose
of any unsuitable underlying material,
- spread fill material in horizontal layers
not more than 250 mm thick, and
- thoroughly compact these layers to required
density.
2.5.2 Preparation of Fill Sites
Fill sites are prepared by removing any material
too weak to support the fill and then compacting the surface by rolling.Where
the natural surface slopes at more than 1 in 4, horizontal terraces will
need to be cut on which to bed the fill.
2.5.3 Excavation of Cuttings
Cuts in softer materials can be made by dozers,
scrapers, excavators and occasionally by graders. In hard materials excavation
by drilling and blasting may be required.
Haulage will usually be by scrapers or by trucks
loaded with a wheeled loader. In rocky materials special rock buggies may
be required. On shorter hauls (up to 100m) it is possible that a dozer may
be able to economically push material from cut to fill.
General principles to be observed in the excavation
of cuttings are:
- provide for drainage during construction;
- establish down-grades so that plant can work
downhill and be assisted by gravity while cutting;
- ensure that cuts are made to the full design
width;
- in through cuts keep the centre high; and
- in side hill cuts keep the inside edge low.
2.5.4 Construction of Fills
Transport of fill material will usually be accomplished
by bulldozers (short hauls), scrapers or trucks. Once the material is deposited
at the fill site it is spread (usually by dozer and/or grader) and, if necessary,
brought to its optimum moisture content by the incorporation of water from
a water cart. Compaction is then carried out using an appropriate roller
or compactor.
General principles to be observed when constructing
embankments:
- ensure that the base of the fill is the correct
width;
- place the material in layers and compact each
layer;
- check the suitability of the fill material
as it arrives;
- ensure that the fill material is at the correct
moisture content for compaction;
- keep the edges of the fill higher than the
centre to prevent material sliding out and to increase safety for plant;
and
- in wet climates crown the fill at the end
of the days work so that any overnight rain will be shed from the work and
will not pond.
2.6 Bridge Construction
Bridges form an integral part of the road system
and from a motorists viewpoint are often the most noticed feature. It is often
necessary to commence bridgeworks ahead of roadworks because bridges are
slower to build. Small bridges may take six months to build whereas large
bridges can take several years.
Compared to other parts of the road, bridges are
expensive. In urban areas the cost of a bridge would usually be at least
five times the cost of an equivalent length of road.
Bridge construction is similar to other structural
construction work (i.e. other steel, reinforced concrete or prestressed concrete
work). This area is not dealt with in this course.
Page last modified 3 July 2003.