Timetable, Semester 2, 1999

Week Date Module - Roads Module - Drainage Assessment
1 19 - 23 July 1. Road Systems and Design
Standards

2. Rural Road Construction

3. Urban Road Construction
and Reconstruction

. .
2 26 - 30 July 4. Pavement Materials 17. Urban Drainage .
3 2 - 6 Aug 5. Pavement Design 17. Urban Drainage .
4 9 - 13 Aug 6. Soil Stabilisation 17. Urban Drainage .
5 16 - 20 Aug 7. Pavement Construction 17. Urban Drainage .
6 23 - 27 Aug 8. Bituminous Materials 17. Urban Drainage .
7 30 Aug - 3Sept 8. Bituminous Materials 17. Urban Drainage .
8 6 - 10 Sept 9. Bituminous Surfacing
Practice
17. Urban Drainage ASSIGNMENT 1

Due 10 Sept. 1999

9 13 - 17 Sept 9. Bituminous Surfacing
Practice
18. Culvert Design .
10 20 - 24 Sept 10. Traffic Control Devices 18. Culvert Design .
11 27 - 30 Sept 11. Street Lighting 18. Culvert Design .
12 4 - 8 Oct 12. Traffic Studies 19. Construction of Drains ASSIGNMENT 2

Due: 8 October 1999

13 11 - 15 Oct 13. Traffic Management

14. Parking Design

19. Construction of Drains .
14 18 - 22 Oct 15. Facilities for Pedestrians
and Cyclists
19. Construction of Drains .
15 25 - 29 Oct 16. Maintenance of Roads
and Streets
19. Construction of Drains .
16 1 - 5 Nov REVISION REVISION .
17 - 19 8 - 26 Nov . . EXAMINATION